Recipient information Input
Total number of customers served by utility / utilities supporting the project 371,979
Total number of residential customers served by utility / utilities supporting the project 322,066
Total number of commercial customers served by utility / utilities supporting the project 49,458
Total number of industrial customers served by utility / utilities supporting the project 455
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program
AMI smart meters installed and operational Quantity* Cost
Total 305,464 $56,419,336
Residential 263,869
Commercial 40,150
Industrial 1,445
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 305,464
Remote connection/disconnection Yes 245,249
Outage detection/reporting Yes 25,985
Tamper detection Yes 135,586
AMI communication networks and data systems Description Cost
Backhaul communications description CVPS:Cellular, terrestrial with a transition underway to a 4G LTE network; GMP:... $4,630,948
Meter communications network CVPS:The Elster Energy Axis AMI System is operational. The Elster system uses...
Head end server CVPS: The Elster Energy Axis system has been deployed; GMP: EA_MS Elster; BED:... $28,062,568
Meter data analysis system BED: The MDMS is a Siemens product called EnergyIP, version 7.2. Siemens Analytics...
Other IT systems and applications CVPS: The MDMS system has also been integrated with the web presentment tool so...
Web portal deployed and operational Quantity* Description
Customers with access to web portal 275,995
Customers enrolled in web portal 24,334 GMP's Web Portal is a Oracle Utilities solution that offers both information at...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A CVPS: Using SEP 1.1 / Zigbee protocol to test in-home displays as part of CPP/PTR... N/A
In home displays 1,091 CVPS:Tendril Insight displays with KWh and peak period notifications currently... $486,316
Energy management device N/A
Direct load control devices 0 Not in the scope of the project. $0
Programmable communicating thermostats
Smart appliances 30 CVPS: CVPS is piloting heat pump water heaters with a small number of customers... $125,288
Customer system communication networks Description
Network characteristics within customer premise CVPS: Using SEP 1.1 / Zigbee protocol to test in-home displays as part of CPP/PTR...
Pricing program Customers with access Customers enrolled Description
Flat Rate167,260167,260
VEC: Per Existing tariff
Flat rate with Peak Time Rebates3,191523
Time of Use Rate10,7373
VEC: Per Existing tariff

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Recipient information Input
Total number of customers served by utility / utilities supporting the project 371,979
Total number of residential customers served by utility / utilities supporting the project 322,066
Total number of commercial customers served by utility / utilities supporting the project 49,458
Total number of industrial customers served by utility / utilities supporting the project 455
Total number of distribution circuits within utility service territory 484
Total number of distribution substations 277
Portion of distribution system with SCADA prior to SGIG/SGD program
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program
Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 33.11% VEC: 64 feeders out of 79 feeders; CVPS: The SCADA deployment is complete. SCADA...
Portion of distribution system with DA due to SGIG/SGD program 13.87% BED: Upgrade is complete; VEC:56 feeders out of 79 feeders; CVPS: Distribution...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 42 BED: BED installed 35 smart relays using the SGIG funding; VEC: VEC installed various DA devices using SGIG funding. (Automated Feeder Switches = 34, Automated Regulators = 88, Feeder monitors = 29, Remote Fault Indicators =2 , Transformer Monitors = 12 an... $2,279,544
Automated capacitors 0 $0
Automated regulators 102 $1,151,324
Feeder monitors 30 $995,776
Remote fault indicators 9
Transformer monitors (line) 12 $7,210,944
Smart relays 276
Fault current limiter 0 $217,260
Other devices 240 $591,662
SCADA and DA communications network Cost
Communications equipment and SCADA $6,752,798
Distribution management systems integration Integrated Description
AMI 0
Outage management system No VEC: AMI is integrated to iVue OMS at 38 additional substations; CVPS: The existing...
Distributed energy resource interface
Other CVPS: The MDMS system has also been integrated with the web presentment tool so...
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) No CVPS: No - RF Fault Indicator pilot previously planned is not being pursued.
Voltage optimization No
Feeder peak load management No
Microgrids
Other functions

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.