Total number of customers served by utility / utilities supporting the project 12,839
Total number of residential customers served by utility / utilities supporting the project 10,956
Total number of commercial customers served by utility / utilities supporting the project 1,864
Total number of industrial customers served by utility / utilities supporting the project 19
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program
AMI smart meters installed and operational Quantity* Cost
Total 12,963 $3,039,800
Residential 11,088
Commercial 1,858
Industrial 17
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 12,963
Remote connection/disconnection Yes 945
Outage detection/reporting Yes 12,963
Tamper detection Yes 12,963
AMI communication networks and data systems Description Cost
Backhaul communications description This project deployed a hybrid fiber optic, Wi-Max, and 200Mhz radio communication... $1,191,600
Meter communications network The grant funded procurement and implementation of Elster’s fixed network AMI...
Head end server Elster Energy Axis MAS AMI head end (EA_MS) is installed. This system provides... $1,115,800
Meter data analysis system The highly configurable meter data management and operational data store enables...
Other IT systems and applications AMI is fully integrated with online customer systems. The first release of customer...
Web portal deployed and operational Quantity* Description
Customers with access to web portal 13,064
Customers enrolled in web portal 4,725 The first release of customer facing web-features was in Q2 2011, and included...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A N/A
In home displays 0 Grounded Power in-home displays were deployed to provide select customers access... $19,400
Energy management device N/A
Direct load control devices
Programmable communicating thermostats
Smart appliances
Customer system communication networks Description
Network characteristics within customer premise
Pricing program Customers with access Customers enrolled Description
Flat Rate12,64212,642
Net Metering 22
Two customers have net metering enabled (1 residential,...
Flat Rate Plus Demand Charges420420

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Recipient information Input
Total number of customers served by utility / utilities supporting the project 12,839
Total number of residential customers served by utility / utilities supporting the project 10,956
Total number of commercial customers served by utility / utilities supporting the project 1,864
Total number of industrial customers served by utility / utilities supporting the project 19
Total number of distribution circuits within utility service territory
Total number of distribution substations
Portion of distribution system with SCADA prior to SGIG/SGD program
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program
Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 94.00% The numerator is the total number of project components configured with SCADA...
Portion of distribution system with DA due to SGIG/SGD program 94.00% The project automates Station 42 and (4) of the (9) 4.16kV substations. These...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 50 The SGIG plan proposes complete automation of Danvers Electric’s 23kV system. The plan included furnishing new, or retrofitting, 28 gang-operated load break switches (GOABS), 22 reclosers, 15 capacitor banks, and 16 feeder monitors. The actual equipme... $1,617,800
Automated capacitors 14 $208,400
Automated regulators
Feeder monitors 12 $185,200
Remote fault indicators 0
Transformer monitors (line) 0 $110,400
Smart relays 0
Fault current limiter
Other devices 8
SCADA and DA communications network Cost
Communications equipment and SCADA $1,206,000
Distribution management systems integration Integrated Description
AMI 0 Integration between the OMS and EA_MS will be done utilizing MultiSpeak protocol....
Outage management system No The OMS business requirements document and Proof of Concept plan for AMI/MDM/OMS...
Distributed energy resource interface No
Other AMI is fully integrated with online customer systems. The first release of customer...
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) No A FDIR application has been configured on the 23kV system to provide automatic...
Voltage optimization No The project included efacec/ACS XpertSim & Power Factor Correction packages. These...
Feeder peak load management
Microgrids
Other functions No Power Factor Correction (formerly known as "Economic Dispatch") is an additional...

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.