| Recipient information | Input |
|---|---|
| Total number of customers served by utility / utilities supporting the project | 12,600 |
| Total number of residential customers served by utility / utilities supporting the project | 7,325 |
| Total number of commercial customers served by utility / utilities supporting the project | 5,200 |
| Total number of industrial customers served by utility / utilities supporting the project | 75 |
| Total number of distribution circuits within utility service territory | 113 |
| Total number of distribution substations | 53 |
| Portion of distribution system with SCADA prior to SGIG/SGD program | 0 |
| Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program | 0 |
| Electric distribution system | % | Description |
|---|---|---|
| Portion of distribution system with SCADA due to SGIG/SGD program | 100.00% | The SCADA portion of the project is 100% complete. PRECorp's system therefore is also 100% complete as no SCADA capability was present prior to this project. SGIG funding made this goal possible. There would be no part of the system with SCADA without SGIG |
| Portion of distribution system with DA due to SGIG/SGD program | 0% | No changes. SGIG funding has no impact on this metric. |
| DA devices installed and operational | Quantity* | Description | Cost |
|---|---|---|---|
| Automated feeder switches | 0 | As of the end of September 2011 there were 15 Automatic Regulators installed as a part of the project. The voltage regulator's electronic control was upgraded with fiber optic communication boards. The project was completed December 2011. | $0 |
| Automated capacitors | 0 | $0 | |
| Automated regulators | 30 | $0 | |
| Feeder monitors | 0 | $0 | |
| Remote fault indicators | 0 | $0 | |
| Transformer monitors (line) | 0 | $0 | |
| Smart relays | 0 | ||
| Fault current limiter | 0 | $0 | |
| Other devices | 0 | $0 |
| SCADA and DA communications network | Cost |
|---|---|
| Communications equipment and SCADA | $2,133,136 |
| Distribution management systems integration | Integrated | Description |
|---|---|---|
| AMI | No | |
| Outage management system | No | |
| Distributed energy resource interface | No | |
| Other | No |
| Distribution automation features / functionality | Function enabled | Description |
|---|---|---|
| Fault location, isolation and service restoration (FLISR) | No | |
| Voltage optimization | No | |
| Feeder peak load management | No | |
| Microgrids | No | |
| Other functions | No |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.