Data reported by:

Pacific Northwest Generating Cooperative

Advanced Meter Infrastructure Implementation Project
Recipient information Input
Total number of customers served by utility / utilities supporting the project 120,865
Total number of residential customers served by utility / utilities supporting the project 106,791
Total number of commercial customers served by utility / utilities supporting the project 12,491
Total number of industrial customers served by utility / utilities supporting the project 1,583
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program
AMI smart meters installed and operational Quantity* Cost
Total 97,281 $22,015,618
Residential 84,852
Commercial 11,134
Industrial 1,295
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 97,281
Remote connection/disconnection Yes 6,416
Outage detection/reporting Yes 74,407
Tamper detection Yes 68,453
AMI communication networks and data systems Description Cost
Backhaul communications description With 9 independent co-ops in this project the Backhaul is diverse.One commonality... $13,751,474
Meter communications network PLC at all co-op locations. The choice to go with PLC was largely driven by the...
Head end server Three types of systems were chosen by the 9 co-ops; Hunt Technologies, Cannon/Cooper... $779,866
Meter data analysis system With 9 independent co-ops in this project the MDA systems are diverse. NISC is...
Other IT systems and applications
Web portal deployed and operational Quantity* Description
Customers with access to web portal 80,799
Customers enrolled in web portal 37,494 As MDM systems are installed, members are bringing up web portals. Co-ops are...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A N/A
In home displays Devices in this category are under consideration. Assessment of the cost benefit...
Energy management device N/A
Direct load control devices Devices in this category are under consideration. Assessment of the cost benefit...
Programmable communicating thermostats
Smart appliances
Customer system communication networks Description
Network characteristics within customer premise

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).