Data reported by:

NRECA-OEC

Enhanced Demand and Distribution Management Regional Demonstration
AMI smart meters installed and operational Quantity* Cost
Total 0 $0
Residential 0
Commercial 0
Industrial 0
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 0
Remote connection/disconnection No 0
Outage detection/reporting No 0
Tamper detection No 0
AMI communication networks and data systems Description Cost
Backhaul communications description $0
Meter communications network
Head end server $0
Meter data analysis system
Other IT systems and applications
Web portal deployed and operational Quantity* Description
Customers with access to web portal 188 SaaS with user tools for member usage and utility analysis.
Customers enrolled in web portal 188 SaaS - usage history, change settings, web chat, etc.
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A Thermostat,water heater, portal, meter & transport N/A
In home displays 2 Purchased and installed 2 at Smart Home Pilot enrollees request. $0
Energy management device 0 0 N/A
Direct load control devices 0 $0
Programmable communicating thermostats 0 $0
Smart appliances 0 0 - none planned with pilot $0
Customer system communication networks Description
Network characteristics within customer premise Thermostat,water heater, portal, meter & transport
Pricing program Customers with access Customers enrolled Description
Time of Use Rate310188
Three level TOD rate approved for pilot
Net Metering 00

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 100.00% Fiber communication in S/S, new RTU, New Regulator controls, upgraded metering,...
Portion of distribution system with DA due to SGIG/SGD program 100.00%
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 2 We installed self healing for two locations for critical customers $0
Automated capacitors 0 $0
Automated regulators 0 $0
Feeder monitors 0 $0
Remote fault indicators 0
Transformer monitors (line) 0 $0
Smart relays 0
Fault current limiter 0 $0
Other devices 0 $0
SCADA and DA communications network Cost
Communications equipment and SCADA $0
Distribution management systems integration Integrated Description
AMI 0
Outage management system No
Distributed energy resource interface No
Other
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) No Yes two installation as noted above in DA
Voltage optimization No Yes plan to evaluate two substation for VVO, if viable will deploy
Feeder peak load management No
Microgrids No
Other functions No

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.