Data reported by:

NRECA-AEC

Enhanced Demand and Distribution Management Regional Demonstration
Web portal deployed and operational Quantity* Description
Customers with access to web portal 8,600 Complete. MDM information is now available to members.
Customers enrolled in web portal 788
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A N/A
In home displays 0 N/A $0
Energy management device 0 N/A
Direct load control devices 0 N/A $0
Programmable communicating thermostats 0 N/A $0
Smart appliances 0 $0
Customer system communication networks Description
Network characteristics within customer premise

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 0.00% 6/24/13 OSI System, Completed, Installed, and Operational.
Portion of distribution system with DA due to SGIG/SGD program 0.00% 2 DA devices are installed and operational as of 10/3/2012. 2 out of 47 fee...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 2 2 DA devices are installed and operational as of 10/3/12. $18,212
Automated capacitors 0 $0
Automated regulators 0 $0
Feeder monitors 0 $0
Remote fault indicators 0
Transformer monitors (line) 0 $0
Smart relays 0
Fault current limiter 0 $0
Other devices 0 $0
SCADA and DA communications network Cost
Communications equipment and SCADA $4,876
Distribution management systems integration Integrated Description
AMI 0
Outage management system No
Distributed energy resource interface No
Other
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) No N/A
Voltage optimization No N/A
Feeder peak load management No N/A
Microgrids No N/A
Other functions No N/A

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.