Electric distribution system | % | Description |
---|---|---|
Portion of distribution system with SCADA due to SGIG/SGD program | 0% | |
Portion of distribution system with DA due to SGIG/SGD program | 0% |
DA devices installed and operational | Quantity* | Description | Cost |
---|---|---|---|
Automated feeder switches | 0 | All capacitors have been installed. | $0 |
Automated capacitors | 938 | $36,767,176 | |
Automated regulators | 0 | $0 | |
Feeder monitors | 0 | $0 | |
Remote fault indicators | 0 | $0 | |
Transformer monitors (line) | 0 | $0 | |
Smart relays | 0 | ||
Fault current limiter | 0 | $0 | |
Other devices | 0 | $0 |
SCADA and DA communications network | Cost |
---|---|
Communications equipment and SCADA | $0 |
Distribution management systems integration | Integrated | Description |
---|---|---|
AMI | No | |
Outage management system | No | |
Distributed energy resource interface | No | |
Other | No |
Distribution automation features / functionality | Function enabled | Description |
---|---|---|
Fault location, isolation and service restoration (FLISR) | No | |
Voltage optimization | No | |
Feeder peak load management | No | |
Microgrids | No | |
Other functions | No |
Electric transmission system | Portion | Description |
---|---|---|
Portion of transmission system covered by phasor measurement systems | 23.00% |
Phasor measurement systems | Quantity* | Description | Cost |
---|---|---|---|
PMUs | 41 | PMUs EHV and Above are defined as those with levels of 345 kV or higher. All PMUs at or above the EHV level have been installed. | $1,607,094 |
Phasor data concentrators | 11 | Make and model, security measures, consistency NASPI and synchrophaso standards, number of PMUs networked. All TO Control Center PDCs have been installed. | $449,806 |
Communications network | All WAN connections from the TO Control Centers to the NYISO's Control Centers have been activated. A new WAN will be constructed for the exchange of phasor data between the Control Centers within the NY Control Area. This WAN will consist of a vendor diverse cloud based topology to include redundant Ethernet routers within each control center that is housing equipment (in this case, phasor data concentrators, PDCs) for the exchange of synchrophasor data. WAN technology to be used is either Multiprotocol Label Switching (MPLS) or virtual Private LAN Services (VPLS). The network is envisioned to include provisioning for a 5 Mb port within each TO control center with a 10 Mb port installed at both of the NYISO control centers. This will have the capacity to support all of the signals that the project is anticipating to deploy (465) and the envisioned 6,640 GB of phasor data that is estimated to be collected by these devices within a year. In addition, a 16 ms latency measure between nodes within the WAN is being targeted. The WAN will be scalable as additional devices are installed, and bandwidth will have the ability to scale accordingly to compensate. The communications medium is envisioned to be a leased line contract that will provide for a fiber handoff from the selected telecommunications providers and an Ethernet interface to the internal (to the control centers) network/s. To date, the project has installed a single WAN provided by a single provider. This WAN utilizes Virtual Private LAN Services (VPLS) and is in place at all NYCA TO control centers that house PDCs. All of the project data is currently being transported on this single WAN. The NYISO, independent of the ARRA funding, will be installing redundancy to this WAN construct in the coming years. The integration of this new data source into existing WANs is strongly being considered. With the advent of the Eastern Interconnect Data Sharing Network, a final design incorporating the NYISO’ | $7,267,478 |
Other transmission assets | Quantity* | Description | Cost |
---|---|---|---|
Dynamic Capability Rating System (DCRS) - Transmission Lines | None | $0 | |
Other transmission assets | $0 | ||
Other transmission assets | 0 | $0 | |
Other transmission assets | 0 | $0 |
Angle/frequency monitoring | Operational | Description | Cost |
---|---|---|---|
Angle/frequency monitoring | Yes | Voltage Stability Monitoring and State Estimation have been deployed to production, and Oscillation Detection is undergoing tuning and validity testing in the Staging Environment in preparation for deployment to production. | $7,908,352 |
Post-mortem analysis (including compliance monitoring) | Yes | ||
Voltage stability monitoring | Yes | ||
Thermal overload monitoring | No | ||
Improved state estimation | Yes | ||
Steady-state model benchmarking | No | ||
DG/IPP applications | No | ||
Power system restoration | No |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.