Total number of customers served by utility / utilities supporting the project 104,175
Total number of residential customers served by utility / utilities supporting the project 92,000
Total number of commercial customers served by utility / utilities supporting the project 12,000
Total number of industrial customers served by utility / utilities supporting the project 175
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program
AMI smart meters installed and operational Quantity* Cost
Total 3,538 $610,687
Residential 3,220
Commercial 318
Industrial 0
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 3,538
Remote connection/disconnection Yes 3,220
Outage detection/reporting Yes 3,538
Tamper detection Yes 3,220
AMI communication networks and data systems Description Cost
Backhaul communications description Mountain House has (2) Verizon Wireless (NAN) neighborhood area network connection,... $0
Meter communications network Mountain House uses Silver Spring Networks Network Interface Card
Head end server Mountain House utilizes Silver Springs Networks UtilityIQ for its AMI headend... $74,150
Meter data analysis system Mountain House utilizes Oracle Hyperion for engineering and rate analysis of meter...
Other IT systems and applications
Web portal deployed and operational Quantity* Description
Customers with access to web portal 102,936
Customers enrolled in web portal 24,072 MID has purchased and installed hardware and software components for back-end...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A N/A
In home displays
Energy management device N/A
Direct load control devices
Programmable communicating thermostats
Smart appliances
Customer system communication networks Description
Network characteristics within customer premise

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Recipient information Input
Total number of customers served by utility / utilities supporting the project 104,175
Total number of residential customers served by utility / utilities supporting the project 92,000
Total number of commercial customers served by utility / utilities supporting the project 12,000
Total number of industrial customers served by utility / utilities supporting the project 175
Total number of distribution circuits within utility service territory 120
Total number of distribution substations 35
Portion of distribution system with SCADA prior to SGIG/SGD program
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program
Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 0.00% MID has Remote Terminal Units (RTUs) at its Prescott Substation that communicate...
Portion of distribution system with DA due to SGIG/SGD program 2.80% Prescott Substation has 5 total distribution breakers that are automated. Additionally,...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 0 Prescott Substation will have 2-way automated Volt/VAR control capability. Substation LTCs will be controlled by OSI software that monitors end-of-line voltage via the Silver Springs Network (SSN) AMI system. Feeder cap banks will be controlled by S&C auto... $0
Automated capacitors 5 $463,908
Automated regulators
Feeder monitors
Remote fault indicators
Transformer monitors (line)
Smart relays
Fault current limiter
Other devices
SCADA and DA communications network Cost
Communications equipment and SCADA
Distribution management systems integration Integrated Description
AMI Nothing at this time.
Outage management system Nothing at this time.
Distributed energy resource interface
Other
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR)
Voltage optimization No Not in operation.
Feeder peak load management
Microgrids
Other functions

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.