AMI smart meters installed and operational | Quantity* | Cost |
---|---|---|
Total | 0 | $0 |
Residential | 0 | |
Commercial | 0 | |
Industrial | 0 |
AMI smart meter features operational | Feature enabled | # of meters with feature |
---|---|---|
Interval reads | No | 0 |
Remote connection/disconnection | No | 0 |
Outage detection/reporting | No | 0 |
Tamper detection | No | 0 |
AMI communication networks and data systems | Description | Cost |
---|---|---|
Backhaul communications description | $0 | |
Meter communications network | ||
Head end server | $0 | |
Meter data analysis system | ||
Other IT systems and applications |
Web portal deployed and operational | Quantity* | Description |
---|---|---|
Customers with access to web portal | 96 | |
Customers enrolled in web portal | 96 | Web and mobile phone interface which gives customers access to data regarding their equipment status (on/off), current flow and pressure data, moisture level data etc. has been developed and is in production. |
Customer systems installed and operational | Quantity* | Description | Cost |
---|---|---|---|
Communication networks and home area networks | N/A | N/A | |
In home displays | 0 | $0 | |
Energy management device | 0 | N/A | |
Direct load control devices | 512 | The Lodestar is an intelligent, remotely controlled power switch designed to monitor and control irrigation pumps and cold storage equipment. It has an internal wireless modem for two-way communications with the automated M2M Network Operations Center and website. The Infinity is a full featured farm system based on M2M Lodestar remotely controlled device. Infinity system provides range of benefits such as water flow and pressure measurements, electric current measurements, soil moisture at multiple depths and locations using wireless communications, temperature and humidity, and any other sensor with a 4-20mA, SDI-12, or other compatible output. | $1,617,080 |
Programmable communicating thermostats | 0 | $0 | |
Smart appliances | 0 | $0 |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.