Data reported by:

FirstEnergy Ohio

Smart Grid Modernization Initiative
AMI smart meters installed and operational Quantity* Cost
Total 34,309 $4,018,602
Residential 31,260
Commercial 3,049
Industrial 0
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 34,309
Remote connection/disconnection N/A
Outage detection/reporting No 0
Tamper detection N/A
AMI communication networks and data systems Description Cost
Backhaul communications description "Backhaul NW for the first 5,000 meters is CDMA using telecom facilities; CDMA... $513,388
Meter communications network Licensed 900 MHz Itron network that provides multipath packet management between...
Head end server The SGMI AMI deployment will use the Itron OWA-ED OpenWay Collection Engine, which... $8,936,338
Meter data analysis system Itron Enterprise Edition will provide the tools to issue, monitor and settle load...
Other IT systems and applications
Web portal deployed and operational Quantity* Description
Customers with access to web portal 2,761
Customers enrolled in web portal 37 Web portal supporting SGMI configuration and customer access/ the web portal is...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A N/A
In home displays 92 In home displays will provide capability to participants with respect to event... $33,406
Energy management device N/A
Direct load control devices 0 Direct load control is managed by the utility via communication with the meter;... $0
Programmable communicating thermostats 473 The Programmable Controllable Thermostat (Energate Z-100 Smart Thermostat) is... $354,326
Smart appliances
Customer system communication networks Description
Network characteristics within customer premise
Pricing program Customers with access Customers enrolled Description
Flat rate with Peak Time Rebates2,7612,761

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.

Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 7.50% For the project area, this value will be calculated as follows: the numerator...
Portion of distribution system with DA due to SGIG/SGD program 100.00% The Programmable Controllable Thermostat is signaled by the utility during program...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 30 The automated switches (this category counts substation reclosers only; line reclosers are counted in ODD #2) will allow for the implementation of automated switching schemes and improve FLISR. Feeder monitors will provide real time monitoring of loads - ... $1,994,476
Automated capacitors 138 $1,081,904
Automated regulators 3 $4,912
Feeder monitors 151 $189,894
Remote fault indicators
Transformer monitors (line)
Smart relays
Fault current limiter
Other devices 98 $337,356
SCADA and DA communications network Cost
Communications equipment and SCADA $6,867,150
Distribution management systems integration Integrated Description
AMI
Outage management system
Distributed energy resource interface
Other
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) Yes The SGMI DA project is built around reducing customer outage minutes. For this...
Voltage optimization Yes SGMI technology will intake data and cycle it through computerized algorithms...
Feeder peak load management Yes SGMI technology will use feeder switching to evaluate and redistribute/balance...
Microgrids
Other functions

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.