Data reported by:

City of Fulton, Missouri

Smart Grid Project
Recipient information Input
Total number of customers served by utility / utilities supporting the project 5,505
Total number of residential customers served by utility / utilities supporting the project 4,539
Total number of commercial customers served by utility / utilities supporting the project 916
Total number of industrial customers served by utility / utilities supporting the project 50
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program
AMI smart meters installed and operational Quantity* Cost
Total 5,505 $1,118,679
Residential 4,539
Commercial 916
Industrial 50
AMI smart meter features operational Feature enabled # of meters with feature
Interval reads 1 5,505
Remote connection/disconnection Yes 4,539
Outage detection/reporting Yes 5,505
Tamper detection N/A
AMI communication networks and data systems Description Cost
Backhaul communications description 3rd Quarter 2014 –Still on hold waiting for poly-phase modules to be delivered.... $10,009
Meter communications network 3rd Quarter 2014 – While waiting for the poly-phase modules we audited all the...
Head end server 2nd Quarter 2014 – Multiple Tantalus upgrades have taken place this past quarter... $592,347
Meter data analysis system
Other IT systems and applications 3rd Quarter 2014 - No change. 2nd Quarter 2014 – Both tap changers are now...
Web portal deployed and operational Quantity* Description
Customers with access to web portal 0
Customers enrolled in web portal 0 3rd Quarter 2014 –Troubleshooting of the webportal is still ongoing but training...
Customer systems installed and operational Quantity* Description Cost
Communication networks and home area networks N/A 1rst Quarter 2014 – No changes will be made to the City's current rate structure... N/A
In home displays
Energy management device N/A
Direct load control devices
Programmable communicating thermostats 1rst Quarter 2014 – No Change 2nd Quarter 2014 – No Change 3rd Quarter 2014...
Smart appliances
Customer system communication networks Description
Network characteristics within customer premise 1rst Quarter 2014 – No changes will be made to the City's current rate structure...
Pricing program Customers with access Customers enrolled Description
Tiered Rate5,5055,505
Existing rates implemented before project. 2nd Q 2014...

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.