Data reported by:

Avista Utilities

Spokane Smart Circuit
Recipient information Input
Total number of customers served by utility / utilities supporting the project 354,554
Total number of residential customers served by utility / utilities supporting the project 313,884
Total number of commercial customers served by utility / utilities supporting the project 39,276
Total number of industrial customers served by utility / utilities supporting the project 1,394
Total number of distribution circuits within utility service territory 330
Total number of distribution substations 206
Portion of distribution system with SCADA prior to SGIG/SGD program
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program
Electric distribution system % Description
Portion of distribution system with SCADA due to SGIG/SGD program 75.00% The portion of the system with SCADA was calculated by taking the total number...
Portion of distribution system with DA due to SGIG/SGD program 21.00% The portion of the project that has Distribution Automation enabled at this time...
DA devices installed and operational Quantity* Description Cost
Automated feeder switches 263 DA Devices include G&W Viper Recloser with SEL 651R relay control, a S&C Scadamate Switch with S&C controller, and a Cooper Capacitor bank with a SEL 2411 controller. All of the DA line devices include a Tropos 802.11 wireless mesh radio. $10,660,794
Automated capacitors 123 $2,125,753
Automated regulators 177 $457,970
Feeder monitors 102 $0
Remote fault indicators
Transformer monitors (line) $4,641,127
Smart relays 102
Fault current limiter $0
Other devices 156,318 $15,958,760
SCADA and DA communications network Cost
Communications equipment and SCADA $6,292,390
Distribution management systems integration Integrated Description
AMI
Outage management system Yes
Distributed energy resource interface
Other
Distribution automation features / functionality Function enabled Description
Fault location, isolation and service restoration (FLISR) Yes Avista is implementing an Application that is called Fault Detection Isolation...
Voltage optimization Yes The system will manage the power factor keeping it within a specified range, and...
Feeder peak load management Yes This application does not have a specific Peak Load Management application. However,...
Microgrids
Other functions No The DA system will include a distributed generation application that will allow...

* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.

* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).

** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.