Recipient information | Input |
---|---|
Total number of customers served by utility / utilities supporting the project | 1,396,751 |
Total number of residential customers served by utility / utilities supporting the project | 1,221,405 |
Total number of commercial customers served by utility / utilities supporting the project | 170,920 |
Total number of industrial customers served by utility / utilities supporting the project | 4,426 |
Total number of distribution circuits within utility service territory | 1,153 |
Total number of distribution substations | 376 |
Portion of distribution system with SCADA prior to SGIG/SGD program | 0 |
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program | 0 |
Electric distribution system | % | Description |
---|---|---|
Portion of distribution system with SCADA due to SGIG/SGD program | 0% | 50 Feeders in the Harrisburg project area have commissioned distribution automation devices installed for use with the Early deployment system. |
Portion of distribution system with DA due to SGIG/SGD program | 4.00% | 214 Cleveland-Price Motor Operators for the airbreak switches, 195 QEI Capacitor Bank controllers and 77 Cooper Vacuum Circuit Reclosers with Form 6 controllers are installed, which is a total of 486 DA devices out of the 486 planned for installation in the project area. |
DA devices installed and operational | Quantity* | Description | Cost |
---|---|---|---|
Automated feeder switches | 214 | 214 Cleveland-Price Motor Operators for the airbreak switches, 195 QEI Capacitor Bank controllers and 77 Cooper Vacuum Circuit Reclosers with Form 6 controllers are installed, which is a total of 486 DA devices out of the 486 planned for installation in the project area. | $8,346,286 |
Automated capacitors | 195 | $775,710 | |
Automated regulators | 0 | $0 | |
Feeder monitors | 0 | $0 | |
Remote fault indicators | 0 | $0 | |
Transformer monitors (line) | 0 | $0 | |
Smart relays | 0 | ||
Fault current limiter | 0 | $0 | |
Other devices | 77 | $3,080,000 |
SCADA and DA communications network | Cost |
---|---|
Communications equipment and SCADA | $10,288,532 |
Distribution management systems integration | Integrated | Description |
---|---|---|
AMI | No | |
Outage management system | No | |
Distributed energy resource interface | No | |
Other | No |
Distribution automation features / functionality | Function enabled | Description |
---|---|---|
Fault location, isolation and service restoration (FLISR) | No | Not deployed/installed to date |
Voltage optimization | No | Not deployed/installed to date |
Feeder peak load management | No | |
Microgrids | No | |
Other functions | No | Not deployed/installed to date |
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.