NSTAR Electric Company
Recipient information |
Input |
||||
Total number of customers served by utility / utilities supporting the project |
1,138,112 |
||||
Total number of residential customers served by utility / utilities supporting the project |
985,885 |
||||
Total number of commercial customers served by utility / utilities supporting the project |
148,356 |
||||
Total number of industrial customers served by utility / utilities supporting the project |
3,871 |
||||
Total number of distribution circuits within utility service territory |
1,960 |
||||
Total number of distribution substations |
194 |
||||
Portion of distribution system with SCADA prior to SGIG/SGD program |
|||||
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program |
|||||
Electric distribution system |
% |
Description |
|||
Portion of distribution system with SCADA due to SGIG/SGD program |
100.00% |
||||
Portion of distribution system with DA due to SGIG/SGD program |
0.00% |
||||
DA devices installed and operational |
Quantity* |
Description |
Cost |
||
Automated feeder switches |
369 |
$14,239,050 |
|||
Automated capacitors |
109 |
$1,273,746 |
|||
Automated regulators |
|
||||
Feeder monitors |
369 |
$0 |
|||
Remote fault indicators |
369 |
||||
Transformer monitors (line) |
|
||||
Smart relays |
|
||||
Fault current limiter |
|
||||
Other devices |
100 |
||||
SCADA and DA communications network |
Cost |
||||
Communications equipment and SCADA |
$0 |
||||
Distribution management systems integration |
Integrated |
Description |
|||
AMI |
|||||
Outage management system |
|||||
Distributed energy resource interface |
|
||||
Other |
|||||
Distribution automation features / functionality |
Function enabled |
Description |
|||
Fault location, isolation and service restoration (FLISR) |
Yes |
||||
Voltage optimization |
Yes |
||||
Feeder peak load management |
Yes |
||||
Microgrids |
|||||
Other functions |
|||||
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.