El Paso Electric Company
Recipient information |
Input |
||||
Total number of customers served by utility / utilities supporting the project |
364,907 |
||||
Total number of residential customers served by utility / utilities supporting the project |
328,553 |
||||
Total number of commercial customers served by utility / utilities supporting the project |
36,306 |
||||
Total number of industrial customers served by utility / utilities supporting the project |
48 |
||||
Total number of distribution circuits within utility service territory |
250 |
||||
Total number of distribution substations |
79 |
||||
Portion of distribution system with SCADA prior to SGIG/SGD program |
|||||
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program |
|||||
Electric distribution system |
% |
Description |
|||
Portion of distribution system with SCADA due to SGIG/SGD program |
1.00% |
||||
Portion of distribution system with DA due to SGIG/SGD program |
2.60% |
||||
DA devices installed and operational |
Quantity* |
Description |
Cost |
||
Automated feeder switches |
13 |
$226,109 |
|||
Automated capacitors |
|||||
Automated regulators |
|
||||
Feeder monitors |
6 |
$82,034 |
|||
Remote fault indicators |
8 |
||||
Transformer monitors (line) |
|
$18,124 |
|||
Smart relays |
8 |
||||
Fault current limiter |
|
||||
Other devices |
8 |
$166,101 |
|||
SCADA and DA communications network |
Cost |
||||
Communications equipment and SCADA |
$264,521 |
||||
Distribution management systems integration |
Integrated |
Description |
|||
AMI |
|||||
Outage management system |
No |
||||
Distributed energy resource interface |
|
||||
Other |
No |
||||
Distribution automation features / functionality |
Function enabled |
Description |
|||
Fault location, isolation and service restoration (FLISR) |
No |
||||
Voltage optimization |
Yes |
||||
Feeder peak load management |
Yes |
||||
Microgrids |
|||||
Other functions |
No |
EPE has no other DA application scheduled at this time. |
|||
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.