Eastern Nebraska Public Power District Consortium
Recipient information |
Input |
||||
Total number of customers served by utility / utilities supporting the project |
6,145 |
||||
Total number of residential customers served by utility / utilities supporting the project |
5,062 |
||||
Total number of commercial customers served by utility / utilities supporting the project |
1,083 |
||||
Total number of industrial customers served by utility / utilities supporting the project |
|||||
Total number of distribution circuits within utility service territory |
68 |
||||
Total number of distribution substations |
20 |
||||
Portion of distribution system with SCADA prior to SGIG/SGD program |
|||||
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program |
|||||
Electric distribution system |
% |
Description |
|||
Portion of distribution system with SCADA due to SGIG/SGD program |
95.00% |
||||
Portion of distribution system with DA due to SGIG/SGD program |
0.00% |
Zero percent. Scheduled to be deployed 2013. |
|||
DA devices installed and operational |
Quantity* |
Description |
Cost |
||
Automated feeder switches |
0 |
$0 |
|||
Automated capacitors |
|||||
Automated regulators |
76 |
$228,399 |
|||
Feeder monitors |
67 |
$1,374,934 |
|||
Remote fault indicators |
|
||||
Transformer monitors (line) |
|
||||
Smart relays |
|
||||
Fault current limiter |
|
||||
Other devices |
|
||||
SCADA and DA communications network |
Cost |
||||
Communications equipment and SCADA |
$2,179,181 |
||||
Distribution management systems integration |
Integrated |
Description |
|||
AMI |
|||||
Outage management system |
|||||
Distributed energy resource interface |
|
||||
Other |
|||||
Distribution automation features / functionality |
Function enabled |
Description |
|||
Fault location, isolation and service restoration (FLISR) |
|||||
Voltage optimization |
|
||||
Feeder peak load management |
|||||
Microgrids |
|||||
Other functions |
|||||
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.