City of Ruston, Louisiana
Recipient information |
Input |
||||
Total number of customers served by utility / utilities supporting the project |
9,930 |
||||
Total number of residential customers served by utility / utilities supporting the project |
8,633 |
||||
Total number of commercial customers served by utility / utilities supporting the project |
1,283 |
||||
Total number of industrial customers served by utility / utilities supporting the project |
14 |
||||
Total number of AMI smart meters installed and operational prior to the SGIG/SGD program |
|||||
AMI smart meters installed and operational |
Quantity* |
Cost |
|||
Total |
10,596 |
$2,757,613 |
|||
Residential |
9,792 |
||||
Commercial |
804 |
||||
Industrial |
0 |
||||
AMI smart meter features operational |
Feature enabled |
# of meters with feature |
|||
Interval reads |
Yes |
10,596 |
|||
Remote connection/disconnection |
Yes |
4,600 |
|||
Outage detection/reporting |
Yes |
10,596 |
|||
Tamper detection |
Yes |
10,596 |
|||
AMI communication networks and data systems |
Description |
Cost |
|||
Backhaul communications description |
$14,227 |
||||
Meter communications network |
900MHZ spread spectrum by Cooper Power. This task is complete. |
||||
Head end server |
$446,438 |
||||
Meter data analysis system |
Harris MeterSense is installed and operational. This task is complete. |
||||
Other IT systems and applications |
Meter data is available to populate GIS mapping. |
||||
Web portal deployed and operational |
Quantity* |
Description |
|||
Customers with access to web portal |
0 |
||||
Customers enrolled in web portal |
0 |
||||
Customer systems installed and operational |
Quantity* |
Description |
Cost |
||
Communication networks and home area networks |
N/A |
N/A |
|||
In home displays |
0 |
$0 |
|||
Energy management device |
0 |
N/A |
|||
Direct load control devices |
|||||
Programmable communicating thermostats |
0 |
$0 |
|||
Smart appliances |
|||||
Customer system communication networks |
Description |
||||
Network characteristics within customer premise |
|||||
| Pricing program | Customers with access |
Customers enrolled |
Description |
||
| Net Metering | 681 | 4 | |||
Distributed energy resources |
Quantity* |
Capacity |
Description |
Cost |
|
Distributed generation |
kW |
PEVs and charge stations were installed in Q3 2012. |
|||
Energy storage |
kW |
||||
Plug in electric vehicle charging points |
2 |
3 kW |
$93,663 |
||
Distributed energy resource interface |
N/A |
N/A |
|||
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.
Recipient information |
Input |
||||
Total number of customers served by utility / utilities supporting the project |
9,930 |
||||
Total number of residential customers served by utility / utilities supporting the project |
8,633 |
||||
Total number of commercial customers served by utility / utilities supporting the project |
1,283 |
||||
Total number of industrial customers served by utility / utilities supporting the project |
14 |
||||
Total number of distribution circuits within utility service territory |
18 |
||||
Total number of distribution substations |
5 |
||||
Portion of distribution system with SCADA prior to SGIG/SGD program |
|||||
Portion of distribution system with distribution automation (DA) prior to SGIG/SGD program |
|||||
Electric distribution system |
% |
Description |
|||
Portion of distribution system with SCADA due to SGIG/SGD program |
0.00% |
Reclosers and capacitors will be SCADA operable. |
|||
Portion of distribution system with DA due to SGIG/SGD program |
0.00% |
||||
DA devices installed and operational |
Quantity* |
Description |
Cost |
||
Automated feeder switches |
0 |
$0 |
|||
Automated capacitors |
0 |
$5,280 |
|||
Automated regulators |
0 |
||||
Feeder monitors |
28 |
$284,212 |
|||
Remote fault indicators |
0 |
||||
Transformer monitors (line) |
0 |
$565,235 |
|||
Smart relays |
28 |
||||
Fault current limiter |
0 |
||||
Other devices |
0 |
||||
SCADA and DA communications network |
Cost |
||||
Communications equipment and SCADA |
$53,836 |
||||
Distribution management systems integration |
Integrated |
Description |
|||
AMI |
No |
SCADA system by ACS |
|||
Outage management system |
No |
N/A |
|||
Distributed energy resource interface |
No |
||||
Other |
No |
Meter data is available to populate GIS mapping. |
|||
Distribution automation features / functionality |
Function enabled |
Description |
|||
Fault location, isolation and service restoration (FLISR) |
No |
Not applicable |
|||
Voltage optimization |
No |
Not applicable |
|||
Feeder peak load management |
No |
Not applicable |
|||
Microgrids |
No |
Not applicable |
|||
Other functions |
No |
Not applicable |
|||
* In some circumstances, costs are incurred before devices are installed resulting in a reported cost where the quantity is zero.
* All dollar figures are the total cost, which is the sum of the federal investment and cost share of the recipient (the recipient cost share must be at least 50% of the total overall project cost).
** In some cases the number of entities reporting is greater than the total number of projects funded by the Recovery Act because some projects have multiple sub-projects that report data. View list of sub-projects.