Convert Planning Model Change Request (PMCR) to Network Operations Model Change Request (NOMCR) V0.9
- Publication Date: December 2010
- Publishing Organization: Electric Power Research Institute
- Format: PDF
- Keywords:
epri use case repository, future change, operational grid, planning group, planning model change request, pmcr, smart grid, transmission service provider, tsp
- Summary:
This is a use case document that describes how a Planning Model Change Request (PMCR) is created by the Transmission Service Provider (TSP) Planning group when a future change in the operational grid is anticipated, expected or planned.